CLARKSVILLE, Tenn. (CLARKSVILLENOW) – Tennessee Department of Transportation (TDOT) road crews have scheduled more blasting work on Warfield Blvd. for Thursday, October 25.
There will be intermittent road closures between Dunbar Cave Road and Stokes Road for pre-split blasting. All traffic will be halted during the blasting process until all debris is removed from roadway.
The $20.6 million project will widen the 2.27-mile stretch of Warfield from three lanes to five lanes with curbs, gutters and sidewalks. The work will include improvements to the intersections at Dunbar Cave Road, Rossview Road, and Ted Crozier Boulevard with additional turn lanes and new, upgraded traffic signals.
Photos: Jim Knoll, CPD